... station will be built across the existing raw water canal , adjacent to the existing raw water pump station ( Fig . 2 ) . Fig . 2 The existing raw water pump station has a capacity of 7 cms and is located on the north bank of the canal ...
... station will be built across the existing raw water canal , adjacent to the existing raw water pump station ( Fig . 2 ) . Fig . 2 The existing raw water pump station has a capacity of 7 cms and is located on the north bank of the canal ...
Side 196
... station will house 5 pumps , each pump rated at 6.6 cms at a head of 3 meters . Ultimately the station will be expanded to house 12 pumps ( 2 spare ) for a total discharge capacity of 66 cms which , with the existing station , will ...
... station will house 5 pumps , each pump rated at 6.6 cms at a head of 3 meters . Ultimately the station will be expanded to house 12 pumps ( 2 spare ) for a total discharge capacity of 66 cms which , with the existing station , will ...
Side 197
... STATION EXISTING PUMP STATION CANAL TO BANGLUANG RESERVOIR 0 10 20 30 M. Hydraulic Design Considerations At low river flow , a significant portion of the total flow is diverted at Sam Lae . The effect of diverting this flow may be to ...
... STATION EXISTING PUMP STATION CANAL TO BANGLUANG RESERVOIR 0 10 20 30 M. Hydraulic Design Considerations At low river flow , a significant portion of the total flow is diverted at Sam Lae . The effect of diverting this flow may be to ...
Indhold
JANUARY | 1 |
Dispersion Estimates off Nobska Point Using | 28 |
Frank A Marston A Memorial | 40 |
Copyright | |
14 andre sektioner vises ikke
Andre udgaver - Se alle
Almindelige termer og sætninger
ACKER annual Area Code 617 argillite Board of Government borings Boston Society BSCE building caissons Chairman Charles Civil Engineers clay Clerk coefficients column Computer Section concrete construction Consulting Engineers Water current meter deflections deterministic developed Drainage Edmund G estimates excavation Executive Committee February 16 flood flow forebay Foundation grid Highways hydraulic hydrologic modeling hydrologic phenomenon hydrologic system John Journal when writing Laboratory March March 22 Mass Massachusetts meeting mention the Journal methods miles ozone Park pier piezometer pipe predicted presented President Herzog problem prototype Prudential Center pump intakes pump station Reports river Robert rock samples SECTION AWARD Sewage shear wall Society of Civil Soil Mechanics Sorota St+1 steel stochastic stochastic process Stone & Webster Street Boston Structural Section Test Embankment transit system Transportation velocity Ven Te Chow vertical watershed writing to Advertisers